Case Study:
FLI were appointed to supply a 30m lattice tower solution, delivering a complete structural package from foundation suitability through to superstructure supply.
Following a GDC suitability check, a generic standard foundation design was adopted using Base Grillage F suitable for a 1.2m deep pad foundation, supplied flat packed for Hiab delivery.
The 30m ATS1301 tower was provided complete with sections A-F, ladder, anti-climb, latchway, feeder brackets and earth lugs, alongside a 2-ring headframe including six 4m antenna poles, nine RRU poles and flooring. Sections A-D were pre-assembled in 5m lengths to streamline erection.
More information on this tower